Anonymized operating example

Phased cleaning launch for a Milton fulfillment centre

How Spotless Canada scoped equipment, safety, temporary facilities and records for an active warehouse launch while the rest of the building was still under construction.

Facility
Fulfillment centre
Location
Milton, Ontario
Year
2026
Program
Phased launch

The client is not named on this page. This example is based on a signed 2026 service proposal and related equipment records.

The challenge

Cleaning during a phased go-live

The first launch area needed service while construction continued elsewhere. Occupancy and access changed week by week, so the program had to scale with the site rather than assume a finished building and a fixed headcount.

Active construction meant shared access routes, changing work zones and strict PPE rules from day one.

Documented initial scope

  • Seven temporary office trailers
  • Four temporary washroom areas
  • Break-room service as facilities came online
  • Floor scrubbing in open phase-one racking rows
  • PPE, WHMIS, SDS and chemical-storage controls
  • Signed check sheets and time-stamped photo logs
How it was planned

Four parts of the launch plan

Each part was set out in writing before service began.

  1. 1

    Scope the first launch area

    Temporary offices, washrooms and break areas were listed with the open racking rows that needed floor care, so service could start before the full building was finished.

  2. 2

    Set safety and access controls

    Site-specific PPE, WHMIS training, SDS access and chemical-storage rules were confirmed before the first shift, alongside construction traffic and access limits.

  3. 3

    Match equipment to the floor

    Tennant ride-on and walk-behind scrubbers were arranged for the open racking aisles and the smaller areas around them.

  4. 4

    Scale with the site

    As occupancy and access changed week by week, the program grew with the building instead of assuming a finished facility and fixed headcount.

What made it work

Controls built in from the start

Safety first

Site-specific PPE requirements and controlled chemical handling were part of the launch plan.

Equipment matched to the floor

Documented rentals included Tennant ride-on and walk-behind scrubbers for the Milton site.

A clear record of the work

Check sheets, photo records and itemized hours gave site leaders a clear completion record.